sschaer
Posted - 09/11/2016 : 09:12:41 finally !!!!
received the approvement from the building inspector. after almost exactly one year
work has already started. removing the old concrete wall was a bit more difficult than expected. but it's done. next week these huge pieces will be lifted down to the road with a huge mobile crane. after that the drilling machine will be lifted up in place. drilling 18 28ft holes in the hill, fill the holes with concrete will be the next tasks. this is necessary to keep the steep hill from sliding down. stay tuned ! more pics will follow.